Case 06

Acceleration vs Mitigation

  • Acceleration
  • Mitigation
  • Programme
All case studies

The commercial question

“The PM says “recover the programme”. Is that Contractor recovery, mitigation or acceleration — and who pays?”

Illustrative scenarios

These are independently created fictional scenarios for professional learning. Figures and conclusions are illustrative, not project-specific assessments or standard rates.

Read the Commercial Desk Disclaimer

Project scenario

NEC4 ECC Option A

A Compensation Event causes a 12-day delay to planned Completion.

The Client/PM wants the Contractor to recover to an earlier position. The Contractor proposes an acceleration package.

Illustrative programme position
ItemBefore the CEAfter implementation
Planned Completion30 November12 December
Completion Date14 December26 December
Terminal float14 days14 days

Contractor position

The Contractor proposes an acceleration package of:

£96,000

Acceleration proposal
Second installation gang£32,000
Night shift premium£18,000
Weekend working£12,000
Additional supervision£9,000
Additional plant£8,000
Logistics / welfare£5,000
Productivity inefficiency£7,000
Risk allowance£5,000
Total£96,000

What would you challenge first?

  • Why is recovery required — Contractor delay or CE-caused delay?

  • Reasonable response / mitigation of a CE is not automatically acceleration.

  • A Client request for an earlier contractual outcome than the properly assessed CE-adjusted position may require consideration of the applicable contractual acceleration process.

  • An acceleration proposal needs a programme story as well as a cost story — the quotation must demonstrate what time the proposed measures are expected to buy.

Key commercial principle

Key commercial principle

“Mitigation reduces the effect of a Compensation Event. Acceleration buys an earlier contractual outcome. They are not the same thing.”

“A CE-caused delay should not simply be absorbed by Contractor-owned terminal float.”

Careful with the acceleration label: If the Client seeks an earlier Completion Date than the properly assessed CE-adjusted Completion Date, this should trigger consideration of the applicable contractual acceleration process rather than being treated automatically as ordinary mitigation.

Commercial Desk headline diagnosis

Commercial Desk headline diagnosis

Programme and acceleration basis requires further review.

One Compensation Event may create multiple effects — direct changed work, labour and resource effects, plant, disruption, resequencing, temporary works, programme delay and prolongation. Those effects are not automatically separate Compensation Events.

Negotiated Clause 36 acceleration quotation

  1. Stage 1 — Underlying CE

    The compensation event is assessed first and separately, including its effect on planned Completion and the Completion Date.

  2. Stage 2 — Clause 36 acceleration

    The PM requests a quotation for an earlier Completion Date. The price is the Contractor's quotation as negotiated and accepted — not an SCC / SSCC CE valuation.

Acceleration is consensual: it takes effect only when the PM accepts the Contractor's quotation and revised programme.

See the Worked Commercial Solution

Full Worked Solution

Part of the upcoming NEC4 Compensation Events Pack.

The Pack includes:

  • Cases 01–06 full Worked Solutions
  • Main Option A–F impact analysis (not six recalculated versions of each Case)
  • Advanced Option B/D Quantity-change Module where applicable
  • Structured evidence and commercial assessment guidance
  • Example response wording

Planned launch price: £79 one-off. No subscription. Coming soon.

Based on the standard NEC4 ECC framework. Always check the applicable Contract Data, secondary Options, Y clauses, Z clauses, local amendments and governing law before applying the worked examples to a live contract.

Related Commercial Desk tools

Programme Assessment

Review the programme basis before using a time period commercially.

Quotation Review

Check whether a CE quotation looks commercially complete.

Commercial Desk is an independent practical reference for construction professionals. It is not affiliated with or endorsed by NEC. It does not reproduce the NEC4 contract and is not a substitute for the applicable executed contract or professional or legal advice. Always check the relevant contract, Contract Data and amendments.