Programme assessment
Review a Compensation Event programme assessment
A structured check of whether a CE time assessment uses the correct contractual programme basis and whether the key time issues have been considered. This tool does not calculate delay, determine entitlement or run critical-path analysis.
Contract and programme position
Dividing date
Programme used for the assessment
Baseline programme quality
Does the programme basis include or identify each item? Not every item is required for a review result.
Actual progress up to the relevant status point
Remaining work logic
Planned Completion
Completion Date
Key Dates, where applicable
Float
Time risk allowance
Relevant access and constraints
Effects of earlier implemented CEs, where applicable
CE effect
Existing delay and actual progress
Planned Completion and Completion Date
Terminal float
Terminal float is the period between planned Completion and the Completion Date shown on the programme.
Different types of float require separate analysis. This tool does not determine ownership of every form of programme float.
Key Dates
Time risk allowance
Mitigation and resequencing
Supporting evidence
Record what you have seen. No documents are uploaded or stored.
Accepted Programme reference / revision
Programme acceptance record
CE notification / instruction
Dividing-date record
Impacted / quotation programme
Narrative / methodology
Logic links
Actual progress records
Site diaries
Progress reports
Key Date evidence, where relevant
Access / constraint records
Previous implemented CE records
Assumptions
Planner explanation / delay analysis
Commercial Desk is an independent practical reference for construction professionals. It is not affiliated with or endorsed by NEC. This tool does not determine delay entitlement, changes to Completion Date or Key Dates, or contractual acceptance of a programme. Always check the applicable executed contract, Contract Data, amendments, Accepted Programme and project records.