Worked examples

Worked Commercial Assessments

See how common NEC4 compensation event issues can be worked through commercially — from the initial submission to cost, time, evidence and the resulting commercial position.

Explore the scenarios for free. Full worked assessments are included in the Compensation Events Pack.

The Pack is coming soon — planned launch price £79 one-off, no subscription.

These are independently created practical scenarios designed to develop commercial reasoning. They are not official NEC worked examples.

Back to CE Desk

Illustrative scenarios

These are independently created fictional scenarios for professional learning. Figures and conclusions are illustrative, not project-specific assessments or standard rates.

Read the Commercial Desk Disclaimer

Start with the commercial problem

  • Case 01 · Disruption Without Delay

    No delay to planned Completion. Does that mean no disruption cost?

    Contractor disruption submission: £29,100

    See what should be challenged when additional gang time, plant, setup, supervision and productivity effects overlap.

    Worked outcome: £20,400 assessed disruption · overall illustrative CE assessment £42,680 including Fee

    Explore the scenario: Case 01
  • Case 02 · Prolongation Cost Caused by a Compensation Event

    21 days of prolongation. Is £57,900 actually supported?

    Contractor submission: £57,900

    See why prolongation is not simply “weeks × preliminaries rate”, and how extended resources are tested individually.

    Illustrative worked assessment: £37,510 including Fee

    Explore the scenario: Case 02
  • Case 03 · Existing Delay + Compensation Event

    The project was already late. The Contractor then submits £194,000 for a later CE.

    Contractor submission: £194,000 before Fee

    See why existing Contractor delay must be separated from the later CE effect — without assuming that the later CE has no effect of its own.

    Key issue: Causation, dividing-date position and double-counting risk

    Explore the scenario: Case 03
  • Case 04 · Omission / Substitution

    £80,000 omitted. £112,000 replacement work. Is the CE simply the difference?

    Contractor net submission: +£38,000 before Fee

    See why the original BoQ value and replacement quotation do not automatically determine the CE valuation.

    Key issue: BoQ value vs change in Defined Cost

    Explore the scenario: Case 04
  • Case 05 · Subcontractor Quotation Review

    A subcontractor quotes £75,000. Can it simply be passed through and Fee added?

    Main Contractor submission: £88,500 + Fee

    See how subcontract liability, credits, substantiation, duplication and Main Contractor additions are reviewed.

    Illustrative worked CE assessment: £68,750 including Fee

    Explore the scenario: Case 05
  • Case 06 · Acceleration vs Mitigation

    The PM wants the programme recovered. Is this mitigation or contractual acceleration?

    Initial acceleration proposal: £96,000

    See how the commercial and programme basis is reviewed before a revised Clause 36 quotation is agreed.

    Accepted acceleration quotation: £82,000 (revised Contractor Clause 36 quotation)

    Explore the scenario: Case 06

These are illustrative worked examples, not project-specific advice. Actual outcomes depend on the contract, amendments, facts, programme position, applicable cost rules and project records.

Cross-case commercial principles

Event ≠ Effect

One Compensation Event can create several cost and time effects. Those effects are not automatically separate Compensation Events.

Causation before valuation

Establish what happened, what changed because of it and what would otherwise have happened before assessing the monetary effect.

Programme first where time matters

Where a Compensation Event includes a time-related cost, establish the programme effect before using that time period as the basis of a commercial assessment.

Commercial Desk is an independent practical reference for construction professionals. It is not affiliated with or endorsed by NEC. It does not reproduce the NEC4 contract and is not a substitute for the applicable executed contract or professional or legal advice. Always check the relevant contract, Contract Data and amendments.