Case 01 · Disruption Without Delay
No delay to planned Completion. Does that mean no disruption cost?
Contractor disruption submission: £29,100
See what should be challenged when additional gang time, plant, setup, supervision and productivity effects overlap.
Worked outcome: £20,400 assessed disruption · overall illustrative CE assessment £42,680 including Fee