Case 04
Omission / Substitution
- Omission
- Substitution
- Option B
The commercial question
“Can the QS simply deduct the original BoQ value and add the replacement quotation?”
Illustrative scenarios
These are independently created fictional scenarios for professional learning. Figures and conclusions are illustrative, not project-specific assessments or standard rates.
Project scenario
NEC4 ECC Option B
Original Scope: 40 precast equipment bases. Original Bill of Quantities value: £80,000.
The PM changes the Scope. The original bases are replaced by 32 larger reinforced in-situ bases requiring reinforcement, formwork, changed lifting arrangements and a revised sequence.
Contractor position
The Contractor submits a net change of:
+£38,000
Net submission before Fee
| Omit original work | −£80,000 |
|---|---|
| Replacement work | +£112,000 |
| Additional supervision | +£6,000 |
| Net submission before Fee | +£38,000 |
What would you challenge first?
The original BoQ value is not automatically the Defined Cost of the omitted work.
The replacement quotation is not automatically the CE valuation.
Not every original cost necessarily disappears when work is omitted.
Additional supervision still requires a demonstrated cost effect.
Key commercial principle
Key commercial principle
“The tender tells you what was priced. The CE assessment asks what Defined Cost changed because of the event.”
“For a substitution, review both sides of the change — what would have happened without the CE and what is forecast to happen with it.”
Commercial Desk headline diagnosis
Commercial Desk headline diagnosis
Assessment basis requires further review.
One Compensation Event may create multiple effects — direct changed work, labour and resource effects, plant, disruption, resequencing, temporary works, programme delay and prolongation. Those effects are not automatically separate Compensation Events.
How the conceptual comparison works
Without CE
Raw resource / cost position → Applicable SCC / SSCC rules → Without-CE Defined Cost
With CE
Raw resource / cost position → Applicable SCC / SSCC rules → With-CE Defined Cost
Identify the CE-caused Defined Cost effect, then apply the applicable Fee treatment.
See the Worked Commercial Solution
Full Worked Solution
Part of the upcoming NEC4 Compensation Events Pack.
The Pack includes:
- Cases 01–06 full Worked Solutions
- Main Option A–F impact analysis (not six recalculated versions of each Case)
- Advanced Option B/D Quantity-change Module where applicable
- Structured evidence and commercial assessment guidance
- Example response wording
Planned launch price: £79 one-off. No subscription. Coming soon.
Based on the standard NEC4 ECC framework. Always check the applicable Contract Data, secondary Options, Y clauses, Z clauses, local amendments and governing law before applying the worked examples to a live contract.
Related Commercial Desk tools
Commercial Desk is an independent practical reference for construction professionals. It is not affiliated with or endorsed by NEC. It does not reproduce the NEC4 contract and is not a substitute for the applicable executed contract or professional or legal advice. Always check the relevant contract, Contract Data and amendments.