Case 03
Existing Delay + Compensation Event
- Existing Delay
- Causation
- Double Counting
The commercial question
“The project was already late before the CE. How much of the later delay actually belongs to the CE?”
Illustrative scenarios
These are independently created fictional scenarios for professional learning. Figures and conclusions are illustrative, not project-specific assessments or standard rates.
Project scenario
NEC4 ECC Option A
Original planned Completion: 30 September.
By the relevant dividing-date assessment position, the project has already experienced Contractor-related delay including late mobilisation, lower-than-planned productivity and a subcontractor resource shortage.
The assessment starts with the Accepted Programme current at the dividing date and the relevant progress, delays and remaining-work position up to that date. In this scenario, that produces a pre-CE forecast planned Completion of 14 October.
A later PM Scope change then causes M&E interface changes, fragmented working, temporary works, resequencing, return visits, lower productivity and later testing activities.
The Contractor forecasts planned Completion after the CE as 11 November.
Contractor position
The Contractor presents the movement from the original 30 September planned Completion to 11 November as approximately six weeks of CE delay. The commercial submission is:
£194,000
Total before Fee
| Direct changed work | £84,000 |
|---|---|
| Disruption | £38,000 |
| Prolongation | £72,000 |
| Total before Fee | £194,000 |
What would you challenge first?
Existing Contractor delay cannot simply be transferred into a later CE.
The relevant dividing-date programme position matters.
Disruption and prolongation may both arise as effects of the same CE.
The same resource or period must not be recovered twice through overlapping disruption and prolongation allowances.
Key commercial principle
Key commercial principle
“Existing delay does not belong to a later CE — but existing delay does not automatically eliminate the later CE’s own effect.”
Commercial Desk headline diagnosis
Commercial Desk headline diagnosis
Significant programme and cost separation required.
One Compensation Event may create multiple effects — direct changed work, labour and resource effects, plant, disruption, resequencing, temporary works, programme delay and prolongation. Those effects are not automatically separate Compensation Events.
How the conceptual comparison works
Without CE
Raw resource / cost position → Applicable SCC / SSCC rules → Without-CE Defined Cost
With CE
Raw resource / cost position → Applicable SCC / SSCC rules → With-CE Defined Cost
Identify the CE-caused Defined Cost effect, then apply the applicable Fee treatment.
See the Full Worked Commercial Assessment
Included in the Compensation Events Pack
Continue into the full worked commercial assessment
The free scenario shows the issue and the key commercial challenges. The full assessment shows how the position is actually worked through.
Inside this worked assessment
- Commercial Position
- Assessment Approach
- Cost / Time Treatment
- Evidence Required
- Worked Commercial Assessment
- Suggested Position
- Example Response
Plus:
- Main Option A–F impact
- Contract-specific checks
See how the £194,000 submission is reconciled: existing Contractor delay is separated from the later CE effect using the Accepted Programme at the dividing date, without assuming the later CE has no effect of its own.
All 6 worked commercial assessments
Planned launch price: £79 one-off. No subscription. Coming soon.
Full worked assessments are unavailable during Free Validation Mode. Coming soon.
Based on the standard NEC4 ECC framework. Always check the applicable Contract Data, secondary Options, Y clauses, Z clauses, local amendments and governing law before applying the worked examples to a live contract.
Related Commercial Desk tools
Programme Assessment
Review the programme basis before using a time period commercially.
Commercial Desk is an independent practical reference for construction professionals. It is not affiliated with or endorsed by NEC. It does not reproduce the NEC4 contract and is not a substitute for the applicable executed contract or professional or legal advice. Always check the relevant contract, Contract Data and amendments.